ATK Highlights Progress On Ares I Crew Launch Vehicle

Changes to increase performance and meet the new flight profile include an enhanced shape of the propellant grain in the forward section, and a larger nozzle throat diameter. The core tooling to be used to achieve the new propellant shape is in manufacturing, as are components for the new nozzle.
by Staff Writers
Minneapolis MN (SPX) Apr 03, 2007
Alliant Techsystems has reported significant progress in developing hardware and materials in support of NASA's new Ares I crew launch vehicle. The Ares I is designed to carry crews to the International Space Station, back to the moon, and on to Mars.

In December 2005, NASA selected ATK to be the prime contractor for design and development of the first-stage propulsion system for the Ares I. The first stage is a five-segment solid rocket booster derived from the four-segment Space Shuttle reusable solid rocket motors (RSRM) developed and produced by ATK.

"We have made tremendous progress over the past year, and the project is on track to conduct ground and flight tests scheduled to begin in 2009," said Ron Dittemore, President, ATK Launch Systems.

The company is primarily using existing RSRM hardware for the new stage, but has added some newly designed components to increase performance and meet a different flight profile. A number of these components are undergoing dimensional checks and verification at ATK's facilities in Utah.

The parts currently being processed are destined for two full-scale engineering process simulation articles which will be shipped to NASA's Marshall Space Flight Center, Ala. in March 2008 to undergo loads testing and analysis of the motor.

Changes to increase performance and meet the new flight profile include an enhanced shape of the propellant grain in the forward section, and a larger nozzle throat diameter. The core tooling to be used to achieve the new propellant shape is in manufacturing, as are components for the new nozzle.

In addition, two mockups of the forward skirt, a section located at the top of the motor between the first and second stages, have also been constructed. The forward skirt is a structural housing for all the first stage electronics. The mockups will simulate the physical space available for the avionics and will be used to determine the optimal required space and placement of the electronics.

Related Links
ATK
Rocket Science News at Space-Travel.Com
Rocket Science News at Space-Travel.Com



Memory Foam Mattress Review
Newsletters :: SpaceDaily :: SpaceWar :: TerraDaily :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News


Anomalous Behaviour Affects Firing Test Of Vega Zefiro 9 Motor
Paris, France (ESA) Mar 30, 2007
On Wednesday 28 March, at around 15:00, the second firing test of the solid rocket motor 'Zefiro 9' - the motor that will power the third stage of ESA's future small launcher Vega - took place at the Salto Di Quirra Inter-force Test Range in Sardinia, Italy.







  • ATK Highlights Progress On Ares I Crew Launch Vehicle
  • Anomalous Behaviour Affects Firing Test Of Vega Zefiro 9 Motor
  • Iowa State To Unveil The Most Realistic Virtual Reality Room In The World
  • Boeing Announces Industry Team For Ares I Crew Launch Vehicle Upper Stage Production

  • Two New Payloads For Ariane 5
  • Proton-M Carrier With Canadian Satellite To Be Launched April 10
  • South Korea Plans To Launch First Rocket In 2008
  • ISRO To Launch Foreign Satellite As Primary Payload First Time

  • Shuttle Assessments And Repair Work Ongoing
  • NASA Assigns Crew For Shuttle Mission To Install Japanese Lab
  • Shuttle Atlantis Grounded by Fuel Tank Damage
  • Marshall Communications And AMERICOM GOVERNMENT SERVICES Extend NASA Contract

  • Crew Moves Soyuz To Prep For New Arrivals
  • Next International Space Station Crew To Launch April 7
  • Soyuz TMA-9 Module Relocation Set For March 30
  • MDA To Implement Space Station Berthing Information Solution For Japan

  • HerOrbit.com Cofounders Are Headed to Space
  • NASA Medical Review Team Appointed
  • New Mexico Voters Weigh Spaceport Tax Impost
  • The First Soyuz Mission Forty Years On

  • China To Pursue Space Instead Of Socialism
  • China Outlines Space Program Till 2010
  • China To Launch New Direct Broadcast Satellite To Replace SinoSat-2
  • Russian Court Upholds Custody For Space Firm Chief Reshetin

  • Machine Shop Keeps Robots Rolling
  • Students Rack Up Wins At Local Robotics Competition
  • Talking Bots
  • Novel Salamander Robot Crawls Its Way Up The Evolutionary Ladder

  • ESA Prepares For A Human Mission To Mars
  • NAU Researchers Find Possible Caves On Mars
  • Spirit Studies Rocks in Vicinity Of Home Plate
  • Opportunity Begins Imaging Of Cape Of Good Hope

  • The content herein, unless otherwise known to be public domain, are Copyright Space.TV Corporation. AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA Portal Reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space.TV Corp on any Web page published or hosted by Space.TV Corp. Privacy Statement